Cramahe Council has approved the awarding of the contract for watermains to serve the new Tim Horton's planned for Big Apple Drive.

Council approved the contract worth $59,735 with the township paying $44,735 of the money. TDL Group, which is completing the Tim Horton's project, will pay the remaining $15,000.

Mayor Marc Coombs asserted that the township normally pays for a portion of this kind of expenditure. Couoncil agreed at its March 17, 2009 meeting to the cost sharing agreement.

Four companies bid on the work.

Cobourg Development Services bid $69,146. Dekeyser Excavating bid $80,505, and Balterre Contracting submitted a bid of $117,401.

Work will begin once TDL Group has signed the paperwork.